M8 Junction 29A

Back to projects

Contract: M8 Junction 29A Drainage Phase 1
Client: D Morgan

Contract Status: Completed in November 2017

Program Duration: 27 Weeks

Celmisa were contracted by D Morgan to undertake all drainage works associated with M8 Junction 29A Phase 1 these works included :

  • Excavation & Installation of approx. 3,000 m of Culvert & Storm water drainage ranging from 150 mm dia – 900 mm dia.
  • Excavation & Installation of manholes & catchpits ranging from 1050 mm dia to 2400 mm dia.
  • Installation of precast head walls to accommodate various pipe diameters. 
  • Supplying additional Plant via Plant hire to support D Morgans in there works.
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

You can adjust all of your cookie settings by navigating the tabs on the left hand side.

View Privacy Policy.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

3rd Party Cookies

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.