Contract: M8 Junction 29A Drainage Phase 1
Client: D Morgan

Contract Status: Completed in November 2017

Program Duration: 27 Weeks

Celmisa were contracted by D Morgan to undertake all drainage works associated with M8 Junction 29A Phase 1 these works included :

  • Excavation & Installation of approx. 3,000 m of Culvert & Storm water drainage ranging from 150 mm dia – 900 mm dia.
  • Excavation & Installation of manholes & catchpits ranging from 1050 mm dia to 2400 mm dia.
  • Installation of precast head walls to accommodate various pipe diameters. 
  • Supplying additional Plant via Plant hire to support D Morgans in there works.