Ellingwood Robroyston

Back to projects

Contract: Ellingwood Robroyston
Client: Advance Construction

Contract Status: Completed in September 2020

Program Duration: 12 Weeks

At Ellingwood Robroyston Celmisa were contracted by Advance Construction to undertake a wide scope of works over a 12 week program which included:

  • Stripping 35,000 M3 of topsoil and haul to various stockpile locations.
  • Carrying out 32,000 M3 of cut to fill earthworks to form platforms for housing.
  • Cut 86,000 M3 of material and haul 800 meters to stockpile.
  • Construct suds pond and topsoil.
  • Construct acoustic bund between site and adjacent M80 Motorway.

 

 

 

 

On this project Celmisa enjoyed great success working with Advance construction, utilizing both company’s broad knowledge and understanding of Trimble Machine control. Using our Trimble guided excavators and dozers we were able to achieve a +/- 20mm accuracy across a detailed site model provided by Advance.