Ellingwood Robroyston

Back to projects

Contract: Ellingwood Robroyston
Client: Advance Construction

Contract Status: Completed in September 2020

Program Duration: 12 Weeks

At Ellingwood Robroyston Celmisa were contracted by Advance Construction to undertake a wide scope of works over a 12 week program which included:

  • Stripping 35,000 M3 of topsoil and haul to various stockpile locations.
  • Carrying out 32,000 M3 of cut to fill earthworks to form platforms for housing.
  • Cut 86,000 M3 of material and haul 800 meters to stockpile.
  • Construct suds pond and topsoil.
  • Construct acoustic bund between site and adjacent M80 Motorway.

 

 

 

 

On this project Celmisa enjoyed great success working with Advance construction, utilizing both company’s broad knowledge and understanding of Trimble Machine control. Using our Trimble guided excavators and dozers we were able to achieve a +/- 20mm accuracy across a detailed site model provided by Advance.

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

You can adjust all of your cookie settings by navigating the tabs on the left hand side.

View Privacy Policy.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

If you disable this cookie, we will not be able to save your preferences. This means that every time you visit this website you will need to enable or disable cookies again.

3rd Party Cookies

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.